Santos has announced a final investment decision to proceed with the Agogo production facility (APF) tie-in project in Papua New Guinea, following approval by the PNG LNG joint venture.

The APF tie-in project will deliver gas from the Santos-operated Agogo production facility to the PNG LNG gas pipeline via a new 19-km pipeline, together with two new wells and associated production facility modifications. Santos’ share of CAPEX is approximately US$160 million (gross capex approximately US$400 million over three years). First gas is targeted 2Q28.

Santos’ CEO and Managing Director, Kevin Gallagher, said the APF tie-in project is a highly value-accretive investment that meets Santos’ disciplined capital allocation criteria and will support Santos’ long-term production profile with a ~12-year production plateau, and the potential to continue production beyond 2050.

“The APF tie-in project is a high-quality development with strong economics and a clear role in our strategy to build and grow portfolio production.

“The execution of this project will convert Santos’ 66 million boe 2P undeveloped reserves into developed reserves, delivering incremental net production of ~54 million ft3/d with significant upside potential depending on reservoir performance.

“With an expected IRR of greater than 50% and a payback period less than four years from FID, and approximately two years from first gas, the project is expected to be strongly value accretive, support our long-term production profile and sustain feed gas supply to PNG LNG,” Gallagher said.

Santos’ Australia and PNG Chief Operating Officer, Brett Darley, added: “Key regulatory approvals are in place, required land access has been secured and all material joint venture approvals have been obtained.

“Through the Santos Foundation and our broader community partnerships, we continue to invest in stronger, more resilient communities in the Highlands and long-term, co-operative relationships with landholders and local stakeholders.

“Our focus is now on progressing detailed design for the facility modification, awarding the two main construction contracts and progressing the temporary construction camp to drive towards first gas in 2Q28,” Darley added.

The project CAPEX is included within CAPEX guidance.

Santos holds a 39.9% interest in the PNG LNG joint venture. Joint venture partners are ExxonMobil PNG Ltd, ENEOS Xplora, Kumul Petroleum, and the Mineral Resources Development Company.

Read the article online at: https://www.lngindustry.com/liquid-natural-gas/12052026/santos-takes-fid-on-agogo-production-facility-tie-in/

Content Original Link:

Original Source LNG INDUSTRY

" target="_blank">

Original Source LNG INDUSTRY

SILVER ADVERTISERS

BRONZE ADVERTISERS

Infomarine banners

Advertise in Maritime Directory

Publishers

Publishers